Research paperFree to read

arXiv preprint (cs.DC) 2024

SCARIF: Towards Carbon Modeling of Cloud Servers with Accelerators

Add an embodied-carbon estimator per server SKU using the SCARIF linear model (5.01 kg per CPU core, 0.16 kg/GB SSD, 0.04 kg/GB HDD, 0.95 kg/GB DRAM, 83.08 kg x (year-2000), intercept -1100), and tag the result as an approximate, vendor-calibrated value.

  • Total embodied carbon of the highest/lowest servers: Dell 1782/1133, HP 3880/423, Lenovo 15593/585 kgCO2e.
Technical guideFree to read

Eaton 2008

Selective Coordination (Cooper Bussmann Electrical Protection Handbook section)

In the coordination checker store device type (fuse class, breaker with or without instantaneous, STD band) and use ratio tables or tested pair tables rather than curves when fault current puts both devices below 0.01 s.

  • Fuse selectivity: load-side total clearing I2t below line-side melting I2t; Low-Peak families need 2:1 amp ratio, other combinations up to 8:1.
Research paperPDF

arXiv (Texas Tech University) 2021

Short Circuit and Arc Flash Study on a Microgrid Facility

In a data-centre LV system with generator backup, run the arc-flash study for both grid-connected and islanded topologies, and check that the much lower islanded fault current (1,296 A instead of 22,793 A) does not lengthen clearing time.

  • A factor of 1.4 was applied to the datasheet maximum short-circuit current of inverter-based sources as a safety band.
Research paperPDF

Fire (MDPI AG) 2023

Simulation Test on Cooling and Fire Suppression with Liquid Nitrogen in Computer Room of Data Center

When assessing non-gas, non-water suppression options, note liquid nitrogen only as a preliminary-stage option, and ask for full-scale testing and an occupant-safety analysis for oxygen depletion before taking design values.

  • Liquid nitrogen extinguished the optical-fibre fire within 3 min and the UPS-component fire within 2 min.
Research paperPDF

Building Simulation (Springer Science and Business Media LLC) 2020

Simulation-based assessment of data center waste heat utilization using aquifer thermal energy storage of a university campus

When considering connecting a data centre to an ATES, make the yearly heat balance (imported versus exported heat) the first feasibility check; a continuously cooling data centre can shift it toward heat rejection.

  • Cooperation with ATES improves average PUE from 1.78 to 1.45.
Research paperFree to read

arXiv (UC Riverside / RIT / Caltech preprint) 2026

Small Bottle, Big Pipe: Quantifying and Addressing the Impact of Data Centers on Public Water Systems

Add a peak-day water demand output (annual average times peaking factor, default at least 2.2 for cooling towers, configurable up to about 6-10 for evaporative assist used only on hot days), and compare it with utility supply capacity in site screening.

  • With a 10% compound annual WUE reduction, the need drops to 227-604 MGD.
Research paperPDF

Energies (MDPI AG) 2026

Smart Reuse of Waste Heat from Data Centres: Energy and Exergy Analysis for a District-Heating Network in Bulgaria

Set data-centre setpoints (air temperature, free-cooling threshold) together with waste-heat sales: warmer setpoints and more free cooling cut cooling electricity by about 45% but also cut recoverable heat to about 45%.

  • Centralised DH heat pumps are cited as giving COP 3-5 for supply temperatures up to 70-80 °C.
White paperFree to read

Schneider Electric 2019

Solving Edge Computing Infrastructure Challenges

Provide an edge/micro data centre template: single-rack bundle of rack, UPS, rack PDU, cooling (passive default), sensors and cameras.

  • Prefabricated modules save about 50% of design and engineering time (WP 163).
Technical guideFree to read

TMMOB Makina Mühendisleri Odası (MMO) 2019

Fire extinguishing system functions and integration with other engineering disciplines (Söndürme Sistemleri Fonksiyonları, Diğer Mühendislik Disiplinleri ile Entegrasyonu)

When a room uses gaseous suppression, require HVAC damper/fan shutdown interlocks, a pressure-relief vent and a 10-minute hold-time integrity test in the commissioning list.

  • For clean-agent rooms, the minimum extinguishing concentration should be held for at least 10 minutes, verified by room integrity testing.

All content and rights belong to the respective authors and publishers. SoSo CAD provides only the citation, its own summary and a link to the source, and is not responsible for the sources' content.

Monthly newsletter · free

Keep your reading list current

Once a month: new library sources, changes to Turkish regulations and upcoming data centre events.