Prediction of Overall Energy Consumption of Data Centers in Different Locations
In siting, do not use PUE as the only criterion; evaluate it together with electricity cost (tariff) and carbon (CUE, grid mix) estimates derived from PUE, since a low-PUE site may have a high tariff or carbon-intensive grid.
- For an assumed 100 million kWh/yr of IT energy, estimated annual electricity cost ranged from $8.1376M (Delinha) to $9.6742M (Yinchuan) among five regions.