Give the sizing engine inputs for minimum load %, maximum voltage and frequency dip, altitude and ambient derate, and per-load type (UPS rectifier pulses, VFD share, motor starting method).
VFD load below about 50% of capacity keeps THD under about 15%.
Import RD 01-21 as parametric AI-hall templates (rack kW, racks per module, module kW, redundancy of fan walls/TMUs/towers, generator and transformer counts) and as golden test cases for capacity math.
Power distribution supports 2N, DR and BR architectures.
Accept humidity limits as dew point plus RH in the environmental envelope settings, default to current ASHRAE recommended values rather than the 2011 ones quoted here, and recommend dew-point control mode for multi-CRAC rooms.
Static buildup: 250 V at 80% RH vs 12,000 V at 20% RH on a raised-floor tile; 1,500 V vs 35,000 V on synthetic carpet.
Catalogue liquid-cooled IT and CDUs with ASHRAE W-class and supply temperature fields, and use these to decide whether compressor cooling can be omitted for the site climate.
Per kW IT versus air baseline: water use down up to 96%, power about 40% lower, CO2 about 39.5% lower.
Link to the observatory from the tool's energy-context panel and take current national and regional data center demand figures from it rather than hard-coding values.
The related PDF reports are CC BY 4.0 and downloaded separately.
In hybrid immersion/direct liquid cooling design, rank dielectric fluids by FOM1, but remember a high-FOM1 fluid can infiltrate the TIM of cold-plated CPUs and raise their temperature.
A near doubling of FOM1 lowered average fluid temperature by approximately 7.7 °C.
Give immersion tank and server catalogue items a field-reliability reference (AFR), and use component-level AFRs in the reliability module rather than assuming immersion degrades availability.
Fleet uptime above 99.999%: about 443 million power-on hours with 1,112 h total downtime.
In liquid-cooling energy calculations, account for glycol concentration (higher pumping power, lower heat transfer) and flow-rate set points, not just supply temperature.
Typical baseline facilities spend about 50% of IT energy on cooling, mostly in chillers and CRAHs.
Build a retrofit wizard asking aisle arrangement (hot/cold yes/no), raised floor (yes/no, depth), drop-ceiling return (yes/no), rack-top-to-ceiling clearance (mm), columns in rows, overhead cabling and existing cooler type, mapped to one of the six containment types.
Containment raises cooling-unit deltaT and can add about 20% or more cooling capacity.
Add rack catalogue fields for door perforation percentage (warn on glass or below the full-perforation spec), rail width versus cabinet width (warn on a 23 in cabinet with 19 in rails and no side seals) and blanking included.
If cabinets in the rows nearest the cooling units run hot (high-velocity plenum flow starving the nearest tiles), consider adjustable underfloor deflectors and grille opening adjustment before fan-assisted tiles (18.1% and 4.9% airflow shift).
The largest drop in average cabinet outlet temperature was 2.81 °C.
Add a processCoupling flag (in_series, in_parallel) to edge sites; for in_series default the availability target to Tier III equivalent and require redundant UPS/cooling (N+1 or 2N) plus maintenance bypass.